The definition of irony……

October 23, 2014

…has to be when it’s too windy to build a wind turbine. The blades have been assembled on the ground and are currently tethered to the crane, but the installation team now need 3 hours of fairly calm weather to lift the assembly into place. The wind speed needs to drop below 6m/s – it is currently 14m/s, with stronger gusts. Great for electricity generation, just not for construction!

DSC_0152


Islay Energy Trust AGM – all welcome

October 21, 2014

Ileach Advert AGM 2014


Real progress!

October 20, 2014

Thursday and Friday saw good progress on site, in relatively calm, clear weather. The tower is  complete, with the nacelle in place. The construction team is now waiting for a break in the weather to attach the blades – this needs 4-5 hours of slightly calmer weather than we have been experiencing over the weekend. Below is a selection of photos from Tony Ashworth, site foreman – I think they speak for themselves!

 

DSC_0097

 

IMG_0943

 

IMG_0951

IMG_0966

 

IMG_0990

 

IMG_0996

 

IMG_1014

 

IMG_1026

 

IMG_1020

 

 

 

 


Turbine arrival at Port Askaig

October 15, 2014

A lovely surprise to get up this morning and find these great photos from Teresa Morris of Islay Wildscapes, who happened to be on the spot when our remaining components arriving yesterday evening.

 

http://islaywildscapes.blogspot.co.uk/2014/10/islay-community-wind-turbine-arrives-at.html

 

Thanks Teresa for allowing us to share this! I will be out on site later today – it’s a bit breezy but we hope construction will be able to get under way.


It’s here!

October 14, 2014

..or at least part of it is – the nacelle and generator arrived today, the tower sections will follow tomorrow. Fingers crossed for some more calm weather!

 

DSC_0097

 

DSC_0095

 

 


Today’s picture…

October 3, 2014

Friday was a busy day , with RJ McLeod and three Islay contractors once again on site, along with a fourth team from Dornoch to mix concrete! The pour went well; the shuttering will be removed in the next few days and the area backfilled.

 

DSC_0058


Firm foundations…

September 30, 2014

Work has been progreesing well at the turbine site, with three Islay contractors and mainland firm RJ MacLeod all on site last week preparing the turbine foundation. The next step will be the concrete pour, scheduled for this Thursday.

 

 

DSC_0523

 

DSC_0527

 

DSC_0526

 

 


%d bloggers like this: