Islay Energy Trust AGM – all welcome

October 21, 2014

Ileach Advert AGM 2014


Real progress!

October 20, 2014

Thursday and Friday saw good progress on site, in relatively calm, clear weather. The tower is  complete, with the nacelle in place. The construction team is now waiting for a break in the weather to attach the blades – this needs 4-5 hours of slightly calmer weather than we have been experiencing over the weekend. Below is a selection of photos from Tony Ashworth, site foreman – I think they speak for themselves!

 

DSC_0097

 

IMG_0943

 

IMG_0951

IMG_0966

 

IMG_0990

 

IMG_0996

 

IMG_1014

 

IMG_1026

 

IMG_1020

 

 

 

 


Turbine arrival at Port Askaig

October 15, 2014

A lovely surprise to get up this morning and find these great photos from Teresa Morris of Islay Wildscapes, who happened to be on the spot when our remaining components arriving yesterday evening.

 

http://islaywildscapes.blogspot.co.uk/2014/10/islay-community-wind-turbine-arrives-at.html

 

Thanks Teresa for allowing us to share this! I will be out on site later today – it’s a bit breezy but we hope construction will be able to get under way.


It’s here!

October 14, 2014

..or at least part of it is – the nacelle and generator arrived today, the tower sections will follow tomorrow. Fingers crossed for some more calm weather!

 

DSC_0097

 

DSC_0095

 

 


Today’s picture…

October 3, 2014

Friday was a busy day , with RJ McLeod and three Islay contractors once again on site, along with a fourth team from Dornoch to mix concrete! The pour went well; the shuttering will be removed in the next few days and the area backfilled.

 

DSC_0058


Firm foundations…

September 30, 2014

Work has been progreesing well at the turbine site, with three Islay contractors and mainland firm RJ MacLeod all on site last week preparing the turbine foundation. The next step will be the concrete pour, scheduled for this Thursday.

 

 

DSC_0523

 

DSC_0527

 

DSC_0526

 

 


At long last…..

August 1, 2014

Four years ago IET didn’t think they would be able to find a suitable site for a Community Wind Turbine, until Scottish Natural Heritage offered one near Glenegedale. As with previous possibilities, this too initially seemed doubtful, because Islay airport was only about four kilometres away, but this turned out not to be a major problem, and the only request from Highlands and Islands Airports Ltd, the operators of the airport, has been to “Please put a red light on top of the turbine!”.

There have of course been numerous hurdles along the way, but that was the turning point which was ultimately to lead to the formation of Islay Energy Community Benefit Society, and the remarkable community response which saw £535,000 raised through the community share offer, 80% from local investors. Now we are beginning at last to see progress on the ground, with the initial civils work completed, and the site ready for Enercon to come and prepare the foundation for the turbine during August. A large area of hardstanding has been created, and a crane pad constructed to accommodate the heavy lifting gear which will raise the turbine components into place. The area for the substation foundation has been concreted and the road widened in places to accommodate the delivery vehicles. Despite some early delays due to legal technicalities, the project is still on schedule for installation during October, and commissioning in November.

Early and ongoing support from Community Energy Scotland, coupled with the technical expertise of Dr Colin Anderson who has acted as technical consultant throughout and is now Project Manager for the construction phase, have been invaluable in this project. Without the support of our investors, however, we would not be at this stage – thanks everyone.

Lindy MacLellan, Project Development Officer, August 2014

OLYMPUS DIGITAL CAMERA


%d bloggers like this: