Wind Power

Islay Energy Trust was instrumental in setting up and implementing the Islay Community Wind Project, and continues to manage the day to day operation of the turbine and the administration of the Islay Energy Community Benefit Fund on behalf of Islay Energy Community Benefit Society.


28th October 2014:


"The wind dropped to a respectable level this morning, and the rotor and blades were lifted into place just after 9am. The Enercon construction team will finish up on site tomorrow – removng crew cabins etc. – and clear the way for the commissioning team. Electrical contractors Prelec are on site today, connecting the turbine to the substation – SSE will then complete their safety tests, and joint the cable which runs to the 11kV line. It’s all coming together!"

Share by: